The Timeline
Completing the development of 210-214 Willett Street will take some time. Check back here to see where we are in the process, and what’s to come.
Tower A
Q4 2026
Anticipated completion date is Q4 2026
30 months
The construction process will take approximately 30 months
Tower B
Q2 2026
Anticipated completion date is Q2 2026
30 months
The construction process will take approximately 30 months
Tower A
Zoning
Q2 2021
Zoning Approval
Q2 2021
Demolition & Excavation Permit
Q3 2021
Complete Building Permit
Q2 2021
Demolition Begins
Q2 2022
Above Grade Construction Begins
Q4 2026
Completion
Q3 2026
Initial Occupancy Projected
Tower B
Zoning
Q2 2021
Zoning Approval
Q1 2023
Excavation Permit
Q1 2023
Complete Building Permit
Q2/Q3 2023
Excavation Begins
Q4 2022
Above Grade Construction Begins
Q2 2026
Completion
Q1 2026
Initial Occupancy Projected